Location : Amiens - Poulainville
Year : 2007
Client : Gazeley
User : Procter and Gamble
Size : Two buildings of 74 000 m² total
This project is the largest the Gazeley-GSE-SAGL team have built so far, with two buildings of
74 000 m² total. It was built in six months.
The project was awarded the "prix de la performance energetique - developpement durable" in 2007 by ASLOG.
The environmental initiatives are as follow:
- Photovoltaic panels for electricity production,
- Solar panels for the offices’ hot water,
- Rainwater re-use system,
- 20 kW wind turbine
- Glu-lam roof and offices structure,
- Increased insulation to warehouse façades,
- Waterless urinals.